Calculation methods

Nuclear & SMR Calculation Methods

Formulas and assumptions behind our nuclear output, fuel cost, SMR, and decommissioning calculators.

Nuclear plant capacity factor & output

Annual Energy Output (MWh/year) = plant capacity (MW) × 8760 × (capacity factor % ÷ 100) · Equivalent Homes Powered = (annual energy output × 1000) ÷ 10,800

This calculator converts the nameplate capacity and capacity factor of a nuclear plant into real annual energy output and an equivalent-homes-powered figure, tying two inputs together: the plant capacity and the capacity factor.

Data sources: U.S. nuclear fleet capacity factor from EIA (Energy Information Administration) annual reports and NERC data; nuclear plant operating characteristics from NRC (Nuclear Regulatory Commission) and industry technical documentation; wind and solar capacity factor benchmarks from EIA and NREL (National Renewable Energy Laboratory); SMR capacity factor projections from vendor technical specifications and DOE (Department of Energy) SMR program documentation; equivalent homes powered calculation based on U.S. average residential electricity consumption (10,800 kWh/year per EIA).

Read the full explanation on the calculator page →

Nuclear plant cooling water usage

Annual Generation (MWh/year) = plant capacity (MW) × 8760 × (capacity factor % ÷ 100) · Annual Water Withdrawal (million gallons/year) = (annual generation × withdrawal rate (gal/MWh)) ÷ 1,000,000 · Annual Water Consumption (million gallons/year) = (annual generation × consumption rate (gal/MWh)) ÷ 1,000,000

This calculator estimates a nuclear plant's annual cooling water withdrawal and consumption by combining its real annual generation with per-MWh withdrawal and consumption rates that depend on cooling technology.

Data sources: Nuclear plant cooling water requirements from USGS (U.S. Geological Survey) and EIA (Energy Information Administration) power plant water use data; once-through vs. cooling tower withdrawal/consumption rates from EPRI (Electric Power Research Institute) and NRC (Nuclear Regulatory Commission) technical reports; thermal efficiency comparisons from EIA and NREL (National Renewable Energy Laboratory); nuclear plant siting considerations from NRC licensing documents and industry technical standards; water use intensity benchmarks from USGS and state water resource agencies.

Read the full explanation on the calculator page →

Nuclear fuel cost

Annual Generation (MWh/year) = plant capacity (MW) × 8760 × (capacity factor % ÷ 100) · Annual Fuel Cost ($) = annual generation (MWh/year) × fuel cost ($/MWh) · Fuel Cost as % of Illustrative Revenue (%) = (annual fuel cost ($) ÷ (annual generation × illustrative wholesale price ($/MWh))) × 100

This calculator converts a nuclear plant's nameplate capacity, capacity factor, fuel cost per MWh, and an illustrative wholesale price into annual generation, annual fuel cost, and fuel cost as a share of illustrative revenue.

Data sources: Nuclear fuel cost benchmarks from EIA (Energy Information Administration) and EPRI (Electric Power Research Institute); uranium supply chain and enrichment costs from World Nuclear Association and U.S. uranium industry data; natural gas fuel cost as share of LCOE from EIA LCOE analysis and NREL studies; nuclear plant economics and fuel cost sensitivity from NRC (Nuclear Regulatory Commission) and industry technical documentation; wholesale electricity price ranges from EIA and regional grid operator data.

Read the full explanation on the calculator page →

SMR levelized cost of electricity (LCOE)

Total Overnight Capital Cost ($) = plant capacity (MW) × 1000 × overnight capital cost ($/kW) · Capital Recovery Factor = (r × (1 + r)^n) ÷ ((1 + r)^n − 1) · Annualized Capital Cost ($/year) = total overnight capital cost ($) × capital recovery factor · Annual Generation (MWh/year) = plant capacity (MW) × 8760 × (capacity factor % ÷ 100) · LCOE ($/MWh) = (annualized capital cost + annual generation × fuel + O&M cost ($/MWh)) ÷ annual generation

This calculator estimates the levelized cost of electricity (LCOE) for a small modular reactor by annualizing its upfront capital cost with a capital recovery factor, adding annual fuel + O&M cost, and dividing the total annual cost by annual generation.

Data sources: SMR capital cost estimates from DOE (Department of Energy) SMR program, NREL (National Renewable Energy Laboratory) techno-economic analyses, and vendor technical specifications; NuScale VOYGR project cost from NuScale technical filings and DOE documentation; FOAK vs. NOAK cost projections from EPRI (Electric Power Research Institute) and industry analyses; nuclear LCOE cost structure from EIA (Energy Information Administration) and NREL; utility-scale solar, wind, and natural gas LCOE benchmarks from EIA and NREL; nuclear fuel cost from EIA and World Nuclear Association.

Read the full explanation on the calculator page →

Data center co-location with nuclear

Annual Nuclear Output (MWh/year) = nuclear plant capacity (MW) × 8760 × (capacity factor % ÷ 100) · Annual Data Center Demand (MWh/year) = target data center continuous load (MW) × 8760 · Coverage (%) = (annual nuclear output ÷ annual data center demand) × 100 · Energy Surplus or Gap (MWh/year) = annual nuclear output − annual data center demand · Max Supportable Continuous Data Center Load (MW) = annual nuclear output ÷ 8760

This calculator compares a nuclear plant's real annual energy output against a data center's annual energy demand, then derives the coverage percentage, the energy surplus or gap, and the maximum continuous load the plant can support.

Data sources: Nuclear capacity factor benchmarks from EIA (Energy Information Administration) and NERC data; data center power demand profiles from industry technical documentation and hyperscaler announcements; Microsoft Three Mile Island / Crane Clean Energy Center agreement from Microsoft and Constellation Energy public filings; Amazon X-energy, Google Kairos Power SMR commitments from company announcements and DOE (Department of Energy) documentation; SMR module capacity ranges from vendor technical specifications; data center backup power requirements from industry standards and technical guidelines.

Read the full explanation on the calculator page →

Nuclear decommissioning reserve (sinking fund)

Future Value of Current Trust Fund Balance ($) = current trust fund balance ($) × (1 + assumed fund investment return (%) ÷ 100)^years remaining · Remaining Future Value Needed ($) = estimated total decommissioning cost ($) − future value of current trust fund balance ($) · Sinking Fund Factor = (assumed fund investment return (%) ÷ 100) ÷ ((1 + assumed fund investment return (%) ÷ 100)^years remaining − 1) · Required Annual Contribution ($/year) = remaining future value needed ($) × sinking fund factor

This calculator estimates how much a nuclear plant licensee must contribute each year to a decommissioning trust fund to reach a target decommissioning cost, accounting for the investment growth of both the existing balance and the ongoing contributions.

Data sources: NRC decommissioning funding regulations (10 CFR 50.75) and guidance documents; individual reactor decommissioning cost estimates from NRC case studies, EPRI (Electric Power Research Institute), and industry technical documentation; historical decommissioning fund investment returns from industry reports and financial data; decommissioning process timelines and scope from NRC licensing documents and completed decommissioning case studies.

Read the full explanation on the calculator page →

Nuclear power uprate

Additional Capacity from Uprate (MW) = current plant capacity (MW) × (uprate percentage (%) ÷ 100) · Uprate Project Cost ($) = additional capacity from uprate (MW) × 1000 × uprate cost per kW ($/kW) · Equivalent New-Build Cost for Same Capacity ($) = additional capacity from uprate (MW) × 1000 × new-build cost per kW ($/kW) · Cost Savings vs. New-Build ($) = equivalent new-build cost ($) − uprate project cost ($) · Cost Savings vs. New-Build (%) = (cost savings ($) ÷ equivalent new-build cost ($)) × 100

This calculator estimates the additional capacity gained from a nuclear power uprate, the cost of the uprate project, the equivalent cost of building that same added capacity from scratch, and the resulting cost savings versus new-build.

Data sources: NRC (Nuclear Regulatory Commission) power uprate approvals and technical documentation; historical uprate capacity additions from NRC and EIA (Energy Information Administration); uprate cost estimates from industry technical reports and EPRI (Electric Power Research Institute); turbine/generator upgrade costs from equipment manufacturers and industry case studies; new-build cost benchmarks from EIA and NREL (National Renewable Energy Laboratory).

Read the full explanation on the calculator page →

SMR vs. traditional large reactor cost comparison

SMR Total Project Cost ($) = target capacity (MW) × 1000 × SMR cost per kW ($/kW) · Traditional Large Reactor Total Project Cost ($) = target capacity (MW) × 1000 × traditional reactor cost per kW ($/kW) · Cost Difference (%) = ((traditional reactor cost per kW − SMR cost per kW) ÷ traditional reactor cost per kW) × 100 · Construction Timeline Difference (months) = traditional reactor construction timeline (months) − SMR construction timeline (months)

This calculator compares the total project cost and construction timeline of a small modular reactor (SMR) deployment against a traditional large reactor built to deliver the same target capacity.

Data sources: SMR cost estimates from DOE (Department of Energy) SMR program, NREL (National Renewable Energy Laboratory) techno-economic analyses, and vendor technical specifications; NuScale UAMPS cost history from NuScale public filings and DOE documentation; Vogtle Units 3 & 4 cost data from Georgia Power and NRC filings; traditional large reactor construction timelines from NRC licensing data and historical project records; SMR construction timeline projections from vendor technical specifications and industry analyses; SMR developer status from company announcements and DOE SMR program tracking.

Read the full explanation on the calculator page →