Back to Data Center
Data Center tools

Data Center Electrical Sizing Calculator

Turn a kW load into three-phase amperage, apply the NEC continuous-load rule, and get first-pass UPS and generator sizing.

Load(kW)
Service voltage (three-phase)
Power factor 0.95
UPS / generator headroom 25%
Load current
633A

kW×1000 ÷ (√3 × V × PF)

Min. circuit rating
791A

NEC 80% continuous rule (÷0.8)

UPS size
658kVA

kVA with headroom

Generator size
625kW

kW with headroom

Results update live as you type. For planning and field-check estimates — always verify against applicable standards and equipment ratings.

Sizing the electrical backbone

Three-phase current follows one formula: amps = watts ÷ (√3 × line voltage × power factor). At 480 V and 0.95 PF, a 500 kW load draws about 633 A. But the number you design conductors and breakers around is larger: the National Electrical Code treats data center loads as continuous (three hours or more), and NEC 210.20/215.3 require overcurrent devices to be sized so the continuous load doesn't exceed 80% of the rating — equivalently, dividing your calculated amps by 0.8.

UPS systems are rated in kVA, so the kW load is divided by power factor before headroom is added; a 20–30% margin covers load growth, battery aging, and the fact that running a UPS near 100% shortens its life and eliminates redundancy. Standby generators are sized in kW with similar headroom, and for large GPU halls the step-load behavior matters — modern accelerators can swing hundreds of kW in milliseconds, which stresses generator governors and is a real topic to raise with your genset vendor.

Treat this as a first-pass estimate for feasibility and interconnection conversations. Actual one-line design — conductor sizing, fault current, selective coordination, transformer impedance — is stamped-engineer territory.

Frequently asked questions