A locational marginal price (LMP) is not one number — it is three: an energy component, a congestion component, and a loss component. A generator settling at a congested node can receive a price far below the regional hub, and that gap, called basis, can quietly erase millions of dollars a year from a project that looked profitable at hub prices. This calculator turns the three LMP components, a reference hub price, and project size into the node LMP, the basis versus the hub in $/MWh and percent, annual energy, and the annual basis impact — the dollars a project earns above or below the hub each year.

Negative where generation is trapped behind a constraint; positive where load is constrained.

Node LMP
$30.00/MWh

energy + congestion + loss

Basis vs Hub
$-12.00/MWh

node LMP − hub price

Basis as % of Hub
-28.6%

basis ÷ hub × 100

Annual Energy
306,600MWh

capacity × 8,760 × CF

Annual Basis Impact
$-3.68M/yr

basis × annual energy (negative earns less than hub)

Results update live as you type. For planning and field-check estimates — always verify against applicable standards and equipment ratings.

How we calculate this →
Insight

A locational marginal price has three parts: energy, congestion and losses. A solar farm behind a congested interface can see a node price far below the hub, so a project that looks profitable at hub prices can lose millions to negative basis. This is why siting and interconnection point matter as much as the technology. Pair this with the Energy Arbitrage Revenue Calculator to see how a battery can lift value at a constrained node; a Virtual PPA / CfD Settlement Calculator can show how a fixed-price contract hedges the basis.

How LMP, basis and annual basis impact are calculated

A locational marginal price (LMP) is the marginal cost of serving one more megawatt-hour of load at a specific grid location, and in organized U.S. wholesale markets it is decomposed into three additive components: energy, congestion, and losses. Node LMP ($/MWh) = Energy Component + Congestion Component + Loss Component. The energy component reflects the system-wide marginal cost of generation; the congestion component is negative where generation is trapped behind a transmission constraint (cheap power cannot reach load, so the local price is depressed) and positive where load is constrained (expensive local generation is needed because cheap imports cannot reach it); the loss component accounts for incremental transmission losses and is typically a small positive or negative value. At the defaults — $40 energy, -$12 congestion, $2 loss — the node LMP is $30/MWh.

Basis vs Hub ($/MWh) = Node LMP − Reference Hub Price. The hub is a liquid reference pricing point for the region; basis is how much a node settles above or below it. At a $42 hub and a $30 node, basis is -$12/MWh, meaning the project receives $12 less per MWh than the hub price. Basis as % of Hub = Basis ÷ Hub Price × 100, which normalizes the gap against the hub level — -$12 on a $42 hub is -28.6%, a large structural discount.

Annual Energy (MWh) = Project Capacity (MW) × 8,760 × Capacity Factor (%) ÷ 100. At 100 MW and a 35% capacity factor (typical of a wind or solar project), annual energy is 306,600 MWh. Annual Basis Impact ($) = Basis × Annual Energy — the total dollars per year the project earns above (positive basis) or below (negative basis) what it would have earned settling at the hub price. At -$12/MWh and 306,600 MWh, the annual basis impact is about -$3.68 million per year: the project earns $3.68M less than a hub-priced contract would suggest. This is why siting and interconnection point matter as much as the technology — a project that looks profitable at hub prices can lose millions to negative basis. Data sources: FERC and ISO/RTO LMP decomposition methodology (PJM, ERCOT, CAISO, MISO, NYISO, ISO-NE); typical wholesale market hub pricing conventions; industry basis and congestion revenue rights (CRR/FTR) hedging practice.

Frequently asked questions

What is LMP?

The price of electricity at a specific grid location, set every five minutes or hourly.

What is basis?

The difference between a node's price and a reference hub price.

What causes negative basis?

Transmission constraints that trap cheap generation in one area.

Can basis be hedged?

Partly, using financial transmission rights or node-settled contracts.