Behind-the-Meter Gas Plant LCOE Calculator
A behind-the-meter gas plant is a 20-year bet on capital, fuel and O&M. Combine installed cost, fixed and variable O&M, heat rate, gas price and discount rate into a single levelized cost of energy ($/MWh), with a cost breakdown and savings versus grid power.
Typical range: $1,500-2,000/kW simple-cycle or engines, $2,200-2,800/kW combined-cycle; costs have risen with turbine shortages.
Optional comparison — the delivered grid price you would pay instead.
capital + fixed O&M + fuel + variable O&M
capacity × 8,760 × CF
(grid price − LCOE) × generation
LCOE cost breakdown
$65.94/MWh total| Component | $/MWh | Share |
|---|---|---|
| Capital | $23.76 | 36% |
| Fixed O&M | $3.17 | 5% |
| Fuel | $34.00 | 52% |
| Variable O&M | $5.00 | 8% |
| Total LCOE | $65.94 | 100% |
Results update live as you type. For planning and field-check estimates — always verify against applicable standards and equipment ratings.
How we calculate this →Fuel is roughly half of a behind-the-meter gas plant's cost at $4 gas, so heat rate and gas price drive the answer. BloombergNEF reports combined-cycle lead times of about five years and costs up 49% versus 2023, which is why developers are bridging with engines and aeroderivative units despite higher heat rates. Redundancy (N+1) and backup are not included. For fuel cost per MWh, see the Heat Rate & Fuel Cost per MWh Calculator; the Turbine Delay Cost Calculator is coming soon.
How behind-the-meter gas LCOE is built
Levelized cost of energy (LCOE) is the average cost per MWh over a plant's life, combining capital recovery, fixed and variable O&M, and fuel. The capital recovery factor (CRF) converts an upfront installed cost into an equal annual payment: CRF = r × (1+r)ⁿ ÷ ((1+r)ⁿ − 1), where r is the weighted average cost of capital (WACC) and n is plant life in years. Annual capital cost = capacity (MW) × 1,000 × installed cost ($/kW) × CRF; at the defaults (100 MW, $2,000/kW, 8% WACC, 25 years) the CRF is about 0.0937 and annual capital is roughly $18.7 million.
Annual fixed O&M = capacity × 1,000 × fixed O&M ($/kW-yr), and annual generation = capacity × 8,760 × capacity factor. Dividing annual capital and fixed O&M by annual generation gives their per-MWh contributions. Fuel cost per MWh = heat rate (Btu/kWh) ÷ 1,000 × gas price ($/MMBtu) — at 8,500 Btu/kWh and $4 gas that is $34/MWh. LCOE = capital/MWh + fixed O&M/MWh + fuel/MWh + variable O&M/MWh, which at the defaults is about $65.9/MWh.
Annual savings versus the grid = (grid price − LCOE) × annual generation — positive when self-generation is cheaper, negative when the grid wins. The model is intentionally simple: it holds fuel price, capacity factor and WACC flat over the plant life, excludes redundancy (N+1 spares), backup fuel, emissions permits, and financing/tax effects, and uses HHV heat rates to match how US gas is billed. For fuel-only economics see the Heat Rate & Fuel Cost per MWh Calculator; for gas volume and pipeline capacity see the Pipeline Gas Supply Requirement Calculator.
Frequently asked questions
What is LCOE?
Levelized cost of energy: the average cost per MWh over the plant's life, combining capital, O&M and fuel.
Does this include redundancy?
No. Firm supply usually needs spare units, which raise cost per MWh.
Why is capital cost so high now?
Turbine and equipment shortages, long lead times and inflation have pushed installed costs up.
Do I need emissions permits?
Usually yes. Air permits add time and cost not modeled here.