Depot Grid Capacity & Service Size Calculator
Grid capacity, not trucks, is often the real constraint on depot electrification. This calculator turns fleet size, daily miles, charger power, and a plug-in window into the peak demand an unmanaged fleet would draw against the same energy delivered by managed charging — then sizes the grid upgrade and electrical service each path needs. Use it before you talk to the utility.
Class 8 electric tractors typically run 1.5–2.5 kWh/mile depending on route and load.
Illustrative; utility upgrade costs vary widely.
managed vs unmanaged peak
within 8-hour window
grid energy after charger losses
fleet daily × 365
Unmanaged vs managed charging
vs available capacity| Metric | Unmanaged | Managed |
|---|---|---|
| Peak | 7,500kW | 2,038kW |
| Shortfall | 6,000kW | 538kW |
| Upgrade cost | $1,500,000 | $134,511 |
| Service size | 7.89MVA | 2.15MVA |
Results update live as you type. For planning and field-check estimates — always verify against applicable standards and equipment ratings.
How we calculate this →Grid capacity, not trucks, is often the real constraint on depot electrification. Fifty trucks on 150 kW chargers could demand 7.5 MW if they all plug in at once, but the same energy delivered across an 8-hour window needs only about 2 MW. Managed charging can cut the required service by roughly 70% and the upgrade bill from about $1.5 million to about $135,000 in this example.
How depot grid capacity and service size are calculated
This calculator sizes the electrical service a fleet depot needs by comparing two charging strategies — every truck charging at once (unmanaged) versus the same energy spread evenly across the available plug-in window (managed) — then pricing the grid upgrade each path requires.
Daily Energy per Truck (kWh) = Miles per Day × Efficiency (kWh/mile) — 150 × 2.0 = 300 kWh. Grid Energy per Truck (kWh) = Daily Energy ÷ (Charger Efficiency ÷ 100) — 300 ÷ 0.92 = 326.1 kWh, accounting for losses in the charger. Fleet Daily Grid Energy (kWh) = Grid Energy per Truck × Number of Trucks — 326.1 × 50 = 16,304 kWh/day.
Unmanaged Peak (kW) = Number of Trucks × Charger Power (kW) × Simultaneity (%) ÷ 100 — 50 × 150 × 1.00 = 7,500 kW. Managed Peak (kW) = Fleet Daily Grid Energy ÷ Plug-In Window (hours) — 16,304 ÷ 8 = 2,038 kW. Peak Reduction (%) = (1 − Managed Peak ÷ Unmanaged Peak) × 100 — (1 − 2,038 ÷ 7,500) × 100 = 72.8%.
Shortfall vs Available Capacity (kW) = MAX(0, Peak − Available Capacity) — unmanaged: MAX(0, 7,500 − 1,500) = 6,000 kW; managed: MAX(0, 2,038 − 1,500) = 538 kW. Upgrade Cost ($) = Shortfall × Upgrade Cost ($/kW) — unmanaged: 6,000 × $250 = $1,500,000; managed: 538 × $250 ≈ $134,500. Service Size (MVA) = Peak ÷ Power Factor ÷ 1,000 — unmanaged: 7,500 ÷ 0.95 ÷ 1,000 = 7.89 MVA; managed: 2,038 ÷ 0.95 ÷ 1,000 = 2.15 MVA.
Hours Needed per Truck = Grid Energy per Truck ÷ Charger Power — 326.1 ÷ 150 = 2.17 hours; if this exceeds the plug-in window, the fleet cannot fully charge even with perfect staggering, and you need more chargers, higher-power chargers, or on-site storage to cover the peak. Annual Energy (MWh) = Fleet Daily Grid Energy × 365 ÷ 1,000 — 16,304 × 365 ÷ 1,000 = 5,951 MWh/yr.
The model assumes a flat load shape during the plug-in window and ignores demand charges, time-of-use energy pricing, and battery state-of-charge constraints. Data sources: U.S. DOE Alternative Fuel Data Center and NREL fleet charging and depot electrification studies; utility interconnection and distribution upgrade cost benchmarks. Verification: with defaults, fleet daily energy 16,304 kWh, unmanaged peak 7,500 kW / shortfall 6,000 kW / $1.5M / 7.89 MVA, managed peak 2,038 kW / shortfall 538 kW / ~$134,500 / 2.15 MVA, 72.8% peak reduction, 2.17 hours per truck, 5,951 MWh/yr.
Frequently asked questions
Why is peak power so much higher than average?
Unmanaged charging lets every truck draw full charger power at once, so the peak is the sum of all chargers rather than the average energy delivered over time.
What is managed charging?
Software that staggers sessions so energy is delivered evenly across the available window, flattening the peak to the fleet's average draw.
Do utilities charge for upgrades?
Often, and timelines can be long. Ask early — distribution upgrades and new service can take months to years to engineer and build.
What if the window is too short?
Add chargers, raise charger power, or use on-site storage to cover peaks the grid cannot serve within the available hours.