Net CONE & Missing Money Calculator
Net CONE (Net Cost of New Entry) is what a new power plant needs to earn from the capacity market to be worth building — its annual fixed cost minus the energy and ancillary margin it would earn anyway. When the capacity price clears below net CONE, the gap is the missing money: the shortfall that keeps new plants from getting built, even at record auction prices. This calculator turns installed cost, WACC, plant life, fixed O&M, energy and ancillary margin, ELCC accreditation, and the capacity price into gross CONE, net CONE per kW-year and per MW-day UCAP, and the missing money per MW-day and per kW-year. Pair it with the Capacity Market Revenue Calculator for the revenue side and the Behind-the-Meter Gas Plant LCOE Calculator for the full cost of self-generation.
Net market margin above fuel and variable cost. See the Spark Spread calculator.
PJM 2028/2029 gas combustion turbine class rating.
PJM's 2028/2029 auction cleared at the $325/MW-day cap. Use your market's price.
Illustrative; PJM's official CONE uses its own reference resource.
CRF 0.0937 × $2,000/kW + fixed O&M
gross CONE − energy & ancillary margin
net CONE ÷ (ELCC ÷ 100) ÷ 365 × 1,000
net CONE UCAP − capacity price
missing money UCAP × ELCC × 365 ÷ 1,000
Results update live as you type. For planning and field-check estimates — always verify against applicable standards and equipment ratings.
How we calculate this →Net CONE is what a new plant needs from the capacity market to be built. At $2,000/kW installed, this example needs about $684 per MW-day of accredited capacity, more than double PJM's $325 cap. That gap is the missing money, and it is why capped auctions can clear short of the reliability requirement even at record prices. For the revenue a plant earns at a given capacity price, see the Capacity Market Revenue Calculator; for the full cost of self-generation, see the Behind-the-Meter Gas Plant LCOE Calculator.
How net CONE and missing money are calculated
Cost of New Entry (CONE) is the annual revenue a new reference power plant needs to recover its capital and fixed operating costs — the price floor below which no rational developer builds. Net CONE subtracts the energy and ancillary margin the plant would earn in the energy market, leaving only the amount that must come from the capacity market. When the capacity auction clears below net CONE, the difference is the missing money: the shortfall that keeps new plants from getting built.\n\nCapital Recovery Factor (CRF) = r × (1+r)^n ÷ ((1+r)^n − 1), where r is the weighted average cost of capital (WACC) and n is the plant life in years. CRF is the annuity factor that converts an up-front capital cost into a level annual payment over the asset's life; at an 8% WACC and 25-year life, CRF ≈ 0.0937. Gross CONE ($/kW-yr) = Installed Cost ($/kW) × CRF + Fixed O&M ($/kW-yr); at $2,000/kW, 0.0937 CRF, and $25/kW-yr fixed O&M, that is about $212.38/kW-yr.\n\nNet CONE ($/kW-yr) = Gross CONE − Energy & Ancillary Margin ($/kW-yr), where the energy and ancillary margin is the net market revenue the plant earns above fuel and variable cost — the Spark Spread & Gas Plant Margin Calculator estimates this. At a $45/kW-yr margin, net CONE is about $167.38/kW-yr. Net CONE ($/MW-day, nameplate) = Net CONE × 1,000 ÷ 365, converting the annual per-kW figure to a daily per-MW figure; at $167.38/kW-yr that is about $458.58/MW-day on a nameplate basis.\n\nCapacity markets pay on accredited capacity (UCAP), not nameplate, so Net CONE ($/MW-day UCAP) = Net CONE per MW-day (nameplate) ÷ (ELCC (%) ÷ 100). At a 67% ELCC — PJM's 2028/2029 gas combustion turbine class rating — the nameplate $458.58/MW-day becomes about $684.45/MW-day UCAP, because each accredited MW must carry the cost of 1/0.67 ≈ 1.49 MW of nameplate. Missing Money ($/MW-day UCAP) = Net CONE UCAP − Capacity Price; at a $325/MW-day capacity price, that is about $359.45/MW-day of shortfall. Missing Money ($/kW-yr) = Missing Money UCAP × (ELCC ÷ 100) × 365 ÷ 1,000, converting back to an annual per-kW figure — about $87.90/kW-yr at the defaults.\n\nThe missing money is why capacity markets with price caps can clear short of the reliability requirement even at record prices: when net CONE exceeds the cap, no new plant covers its cost, so the auction clears without enough new capacity and regulators must intervene. ELCC matters because capacity is paid on accredited MW — a lower ELCC rating raises the per-UCAP-MW price a plant needs, which is why lower-accredited resources face a higher net CONE hurdle. This calculator is illustrative; PJM's official CONE uses its own reference resource, cost assumptions, and accreditation methodology. Data sources: PJM 2028/2029 Base Residual Auction clearing price ($325/MW-day cap); PJM 2028/2029 ELCC class ratings (gas combustion turbine 67%); CRF / annuity capital recovery methodology from engineering economics; CONE and net CONE methodology from PJM and FERC capacity market filings. Verification: $2,000/kW, 8% WACC, 25-year life, $25/kW-yr fixed O&M, $45/kW-yr energy margin, 67% ELCC, $325/MW-day capacity → CRF 0.0937, gross CONE ≈ $212.38/kW-yr, net CONE ≈ $167.38/kW-yr, net CONE UCAP ≈ $684.45/MW-day, missing money ≈ $359.45/MW-day UCAP, missing money ≈ $87.90/kW-yr.
Frequently asked questions
What is CONE?
Cost of New Entry: the annual cost of building and running a new reference plant.
What is net CONE?
CONE minus the energy and ancillary margin the plant would earn.
What is missing money?
The shortfall between what a new plant needs and what the market pays.
Why does ELCC matter?
Capacity is paid on accredited MW, so a lower rating raises the price needed per UCAP MW.