Mining Farm Power & Fleet Sizing Calculator
Size a Bitcoin mining farm from the grid connection down. Enter your site power capacity and cooling type, pick a miner, and this calculator converts megawatts into miner count, fleet hashrate, network share, and the daily revenue, power cost, and net the farm earns — using the full facility load (including cooling) for power cost.
PUE values are typical planning estimates.
site MW ÷ PUE
IT load ÷ miner power
0.791 EH/s
fleet EH/s ÷ network EH/s
site MW ÷ power factor
0.3591 BTC × price
full facility load
after pool fee + power
net/day × 30.4
net/day × 365
net ÷ revenue
| IT load | 8.70MW |
| Number of miners | 2,486 |
| Fleet hashrate | 790.5PH/s |
| Network share | 0.000791% |
| Utility demand | 10.5MVA |
| Gross BTC / day | 0.35909BTC |
| Revenue / day | $30,522.70 |
| Pool fee / day | $610.45 |
| Energy / day | 235,200kWh |
| Power cost / day | $16,464.00 |
| Net / day | $13,448.25 |
| Net / month | $408,826.75 |
| Net / year | $4,908,611 |
| Margin | 44.1% |
Planning-level estimate. Real sites also need transformer, switchgear, cooling and networking design by a qualified engineer. Defaults reflect October 2026 network conditions — update BTC price, hashrate and fees before relying on results.
Results update live as you type. For planning and field-check estimates — always verify against applicable standards and equipment ratings.
How we calculate this →How a mining farm is sized from megawatts
A mining farm is sized from the grid connection down, and the first conversion is the one most people get wrong: the site power capacity is the total facility draw, not the IT load. Cooling and power delivery overhead — captured by PUE — sit on top of the miners, so the power actually available to the ASICs is IT load (MW) = site MW ÷ PUE. A 10 MW site with air cooling at PUE 1.15 leaves 8.70 MW for the miners; immersion at PUE 1.08 leaves 9.26 MW. Lower PUE means more miners on the same interconnection, which is why liquid cooling is not just an efficiency choice at scale — it is a revenue decision.
Number of miners = IT load in watts ÷ miner power draw, rounded to the nearest whole unit. Fleet hashrate (PH/s) = miners × TH/s ÷ 1,000, and the fleet's share of the network = fleet EH/s ÷ network EH/s — the same share calculation used in the ASIC Miner Profitability Calculator, just scaled up from one machine to the whole farm. Revenue/day = share × 144 × subsidy × (1 + fee%) × uptime × BTC price, and pool fee = revenue × pool fee %.
Power cost is where this calculator differs from the single-miner tools: it prices the full facility load, not just the miners. Power cost/day = site MW × 1,000 × 24 × uptime × $/kWh, because the utility meters everything — IT load plus cooling, UPS losses, and building systems. Net/day = revenue − pool fee − power cost, with monthly (×30.4) and annual (×365) projections. Utility demand (MVA) = site MW ÷ power factor, the apparent power the transformer and switchgear must be sized to deliver — real power divided by power factor, since the grid must carry the reactive component too.
Two practical notes. First, the miner count is a nameplate fit — it assumes every miner draws exactly its rated power and the facility can balance the load across phases, which real deployments rarely achieve perfectly. Second, network share is a snapshot: as more hashrate joins the network, your farm's share — and therefore its revenue — falls even if you add nothing, which is why difficulty growth matters more for a farm than for a single miner.
Frequently asked questions
How many miners can I run per megawatt?
It depends on the miner's power draw and your site's PUE. The power actually available to the ASICs is site MW ÷ PUE, so a 1 MW air-cooled site (PUE 1.15) leaves about 870 kW of IT load. Dividing that by a miner's power draw gives the count — for Antminer S23s at 3,498 W, that is roughly 248 miners per megawatt of air-cooled capacity, or about 264 per megawatt with immersion cooling at PUE 1.08.
What is PUE for a mining farm?
PUE (Power Usage Effectiveness) is total facility power divided by IT power — the overhead a site spends on cooling, power conversion, and building systems on top of the miners. Air-cooled mining farms typically run PUE 1.10–1.25; immersion and hydro-cooling push lower, toward 1.05–1.10, because liquid removes heat far more efficiently than air. Lower PUE means more miners on the same grid connection, which is why cooling architecture is a revenue decision at scale.
Why does cooling type change the number of miners?
Because the site power capacity is fixed, and cooling overhead competes with the miners for it. A higher PUE means more of your megawatts go to chillers and fans rather than ASICs, so fewer miners fit. Switching from air cooling (PUE 1.15) to immersion (PUE 1.08) on a 10 MW site raises the IT load from 8.70 MW to 9.26 MW — roughly 160 extra S23s, and the revenue they produce, on the exact same interconnection.
How much of the network hashrate would my farm represent?
Network share = your fleet's EH/s ÷ total network EH/s. A 10 MW air-cooled S23 farm at the defaults holds about 0.79 EH/s, which is roughly 0.079% of a 1,000 EH/s network — small in percentage terms, but enough to move revenue meaningfully as difficulty changes. Because share is relative, your farm's revenue falls whenever the network grows, even if you add hashrate yourself, which is why difficulty growth matters more for a farm than for a single miner.