Calculation methods

Data Center & Crypto Mining Calculation Methods

Formulas and assumptions behind our AI data center, cooling, GPU power, and Bitcoin mining calculators.

GPU / compute power load

IT Load (kW) = TDP (W) × Utilization × Chip Count ÷ 1000

Thermal Design Power (TDP) is the manufacturer's maximum sustained power rating per chip. Real-world training and inference workloads rarely peg every chip at 100%, so the calculator applies a utilization factor. The result is IT load — the power the compute hardware itself draws, before cooling and facility overhead are added via PUE.

Used by: GPU & Compute Power Load Calculator, AI Training Energy Calculator, Inference Tokens-per-Watt Calculator

Data center cooling & PUE

Total Facility Power (kW) = IT Load (kW) × PUE

Power Usage Effectiveness (PUE) expresses how much energy a facility spends on cooling, power distribution, and other overhead for every watt delivered to compute. A PUE of 1.0 is impossible in practice; 1.2–1.4 is typical for modern hyperscale designs, while older air-cooled facilities run 1.6–2.0. Cooling load in tons is derived from the heat that must be rejected, converted through the BTU relationship below.

Used by: Data Center Cooling Load Calculator, PUE & AI Efficiency Calculator, Data Center Power Cost & TCO Calculator, Liquid vs. Air Cooling Calculator, Data Center Water Usage Calculator

Heat and cooling capacity

1 kWh = 3,412 BTU · 1 ton of cooling = 12,000 BTU/h ≈ 1–1.2 kW electrical

Nearly all electrical energy consumed by IT equipment or appliances is ultimately rejected as heat. Converting that heat load into BTU/h and then into tons of cooling lets our tools size air conditioning and chiller capacity, and estimate the electrical draw of the cooling system itself.

Used by: HVAC Energy Cost Calculator, Smart Thermostat Savings Calculator

Fuel cell sizing & cost

Installed capacity = target power × units (1 for N, 2 for N+1/2N) · Capex = capacity (kW) × $/kW × (0.70 if ITC) · Fuel (MMBtu) = (MWh × 3.412) ÷ efficiency

Fuel cell sizing mirrors transformer redundancy logic: N installs one system sized to the full target load, while N+1 and 2N both install two units each sized to the full load — so total installed capacity is 2× the target. Capital cost is total installed kW × installed $/kW, reduced by a 0.70 multiplier when the 30% Section 48E Investment Tax Credit applies. Annual output uses the target power (not total installed capacity, since the N+1 standby does not generate), multiplied by 8760 hours and the capacity factor. Annual natural gas consumption converts that output through the EPA combustion constant 3.412 MMBtu/MWh and divides by system electrical efficiency (35–65% LHV for SOFC). Levelized fuel cost is annual fuel cost ÷ annual output.

Open the calculator →

Interconnection delay cost

Delay avoided (mo) = (utility yrs − on-site yrs) × 12 · Opportunity cost = MW × $/MW-mo × delay · On-site premium = MW × 1000 × $/kW · Net = opportunity − premium · Breakeven (mo) = premium ÷ (MW × $/MW-mo)

The model weighs the value of time against the cost of buying it back. Delay avoided (months) is the interconnection timeline you reclaim by building on-site generation instead of waiting in the utility queue: (standard utility timeline in years − on-site alternative timeline in years) × 12. Opportunity cost of waiting ($) = target power (MW) × opportunity value ($/MW-month) × delay avoided — where the opportunity value reflects revenue, lease rates, or cost of capital per megawatt-month (2026 hyperscale/wholesale colocation rates run roughly $100,000–250,000/MW-month). On-site capital cost premium ($) = target MW × 1,000 × $/kW premium, the extra up-front capital paid for speed. Net financial benefit = opportunity cost − on-site premium; positive means going on-site sooner is favorable at the assumptions entered. Breakeven delay avoidance (months) = on-site premium ÷ (MW × $/MW-month), the minimum delay avoidance needed to justify the premium. The comparison covers capital premium and opportunity cost only — it excludes ongoing fuel, maintenance, and operating costs of on-site generation.

Open the calculator →

ASIC miner profitability

Share = (TH/s × 1e12) ÷ (network EH/s × 1e18) · Gross BTC/day = share × 144 × subsidy × (1 + fee%) × uptime × qty · Revenue/day = gross BTC × BTC price · kWh/day = (W ÷ 1000) × 24 × uptime × qty · Net/day = revenue − pool fee − power cost · Breakeven $/kWh = (revenue − pool fee) ÷ kWh/day

Bitcoin mining revenue is a miner's share of the daily block rewards the network pays out. Share = (miner hashrate in TH/s × 1e12) ÷ (network hashrate in EH/s × 1e18), converting both to raw hashes per second. Gross BTC/day = share × 144 blocks/day × block subsidy (BTC) × (1 + transaction fees as % of subsidy) × uptime × quantity — the fee term folds in transaction fees, and uptime scales revenue down for downtime. Revenue/day = gross BTC/day × BTC price. Pool fee/day = revenue × pool fee %. Energy/day = (power W ÷ 1000) × 24 × uptime × quantity, and power cost/day = energy × electricity $/kWh. Net/day = revenue − pool fee − power cost. Margin % = net ÷ revenue. Breakeven electricity price = (revenue − pool fee) ÷ kWh/day — the rate at which net falls to zero. Defaults reflect October 2026 network conditions (BTC ~$85,000, network ~1,000 EH/s, 3.125 BTC subsidy post-2024 halving); update price, hashrate, and fees before relying on results. Verification: Antminer S23 (318 TH/s, 3,498 W), all defaults, qty 1 → gross BTC/day = 0.0001444, revenue = $12.28/day, pool fee = $0.25, power cost = $5.76 (82.3 kWh), net = $6.27/day, annual ≈ $2,290, margin = 51%, breakeven ≈ $0.146/kWh.

Used by: ASIC Miner Profitability Calculator, ASIC Efficiency Comparison Calculator

Mining farm power & fleet sizing

IT load (MW) = site MW ÷ PUE · Miners = round(IT load in W ÷ miner W) · Fleet PH/s = miners × TH/s ÷ 1000 · Network share % = (fleet EH/s ÷ network EH/s) × 100 · Utility demand (MVA) = site MW ÷ power factor · Revenue/day = share × 144 × subsidy × (1 + fee%) × uptime × BTC price · Power cost/day = site MW × 1000 × 24 × uptime × $/kWh · Net/day = revenue − pool fee − power cost

A mining farm is sized from the grid connection down. The site power capacity is the total facility draw, not the IT load — cooling and power delivery overhead (captured by PUE) sit on top of the miners — so IT load (MW) = site MW ÷ PUE. A 10 MW site with air cooling at PUE 1.15 leaves 8.70 MW for the ASICs; immersion at PUE 1.08 leaves 9.26 MW. Number of miners = round(IT load in watts ÷ miner power draw), rounded to the nearest whole unit. Fleet hashrate (PH/s) = miners × TH/s ÷ 1,000, and fleet EH/s = PH/s ÷ 1,000. Network share (%) = (fleet EH/s ÷ network EH/s) × 100 — the same share calculation used in the ASIC Miner Profitability Calculator, scaled from one machine to the whole farm. Revenue/day = share × 144 × subsidy × (1 + fee%) × uptime × BTC price; pool fee/day = revenue × pool fee %. Power cost/day = site MW × 1,000 × 24 × uptime × $/kWh — the full facility load (IT plus cooling, UPS losses, and building systems), because the utility meters everything the site draws. Net/day = revenue − pool fee − power cost; monthly = net/day × 30.4; annual = net/day × 365. Utility demand (MVA) = site MW ÷ power factor, the apparent power the transformer and switchgear must deliver. Verification: 10 MW, air-cooled PUE 1.15, Antminer S23 (318 TH/s, 3,498 W), defaults → IT load = 8.70 MW, 2,486 miners, fleet = 790.5 PH/s (0.79 EH/s), network share = 0.079%, utility demand = 10.5 MVA.

Open the calculator →

Hashprice & breakeven

BTC/PH/s/day = (1e15 ÷ (EH/s × 1e18)) × 144 × subsidy × (1 + fee%) · Hashprice ($/PH/s/day) = BTC/PH/s/day × BTC price · sats/TH/day = BTC/PH/s/day × 1e8 ÷ 1000 · kWh/TH/day = (J/TH × 86400) ÷ 3,600,000 · Breakeven $/kWh = (hashprice ÷ 1000) ÷ kWh/TH/day · Breakeven BTC price = (kWh/TH/day × $/kWh) ÷ (BTC/PH/s/day ÷ 1000) · Margin = 1 − (power cost/TH/day ÷ revenue/TH/day)

Hashprice is the revenue a unit of Bitcoin mining power earns per day, set entirely by the network — BTC price, total network hashrate, the block subsidy, and transaction fees — and independent of any specific miner. BTC per PH/s per day = (1e15 ÷ (network EH/s × 1e18)) × 144 × subsidy × (1 + fee%): the first term is one petahash's share of total network hashrate (both in raw hashes/second), 144 is the roughly one block per ten minutes the network produces daily, and the fee term folds transaction fees in as a percentage of the subsidy. At the defaults (1,000 EH/s, 3.125 BTC, 3% fees) that is 0.0004635 BTC per PH/s per day. Hashprice ($/PH/s/day) = BTC per PH/s per day × BTC price — about $39.40 at $85,000. In sats, Hashprice (sats/TH/day) = BTC per PH/s per day × 1e8 ÷ 1000, since one PH/s is 1,000 TH/s and one BTC is 100M sats — about 46.4 sats/TH/day. The breakeven electricity price is the highest $/kWh at which mining still covers its power cost: kWh per TH per day = (J/TH × 86,400) ÷ 3,600,000 (efficiency in joules per terahash times seconds per day, converted to kWh), and Breakeven electricity ($/kWh) = (hashprice ÷ 1000) ÷ kWh per TH per day, dividing hashprice by 1,000 to express it per TH rather than per PH — about $0.149/kWh at 11 J/TH and a $39.40 hashprice. Breakeven BTC price = (kWh per TH per day × $/kWh) ÷ (BTC per PH/s per day ÷ 1000) — about $39,900 at 11 J/TH and $0.07/kWh. Margin at current inputs = 1 − (power cost per TH/day ÷ revenue per TH/day). The efficiency table shows breakeven electricity climbing as miners get less efficient: 9.5 J/TH breaks even near $0.173/kWh while 25–30 J/TH older-generation machines need power below roughly $0.06/kWh. Verification: defaults (BTC $85,000, 1,000 EH/s, 3.125 BTC, 3% fees, 11 J/TH, $0.07/kWh) → hashprice ≈ $39.40/PH/s/day, ≈ 46.4 sats/TH/day, breakeven electricity ≈ $0.149/kWh, breakeven BTC price ≈ $39,900.

Open the calculator →

Hosting vs self-hosting cost comparison

Revenue/day (after pool fee) = (TH/s × 1e12 ÷ (EH/s × 1e18)) × 144 × subsidy × (1 + fee%) × uptime × qty × BTC price × (1 − pool fee%) · kWh/day = (W ÷ 1000) × 24 × uptime × qty · Self-hosted all-in $/kWh = energy price × PUE + (fixed + O&M) × 12 ÷ (8760 × uptime) + (capex/kW ÷ life) ÷ (8760 × uptime) · Net/day = revenue − cost/day · Annual cost/MW = 1000 × 8760 × uptime × $/kWh · Breakeven self-hosting energy = (hosting rate − fixed/O&M/capex per kWh) ÷ PUE

This calculator holds the mining economics constant and varies only how the power is priced, so the two options — paying an all-in hosting rate versus building and operating your own site — are compared on equal footing. Revenue is identical for both: revenue/day (after pool fee) = (miner hashrate in TH/s × 1e12 ÷ (network hashrate in EH/s × 1e18)) × 144 × subsidy × (1 + fee%) × uptime × quantity × BTC price × (1 − pool fee%). Energy/day = (power W ÷ 1000) × 24 × uptime × quantity. The two options then diverge on cost. Hosting is a single all-in $/kWh — the turnkey rate a hosting operator charges covering power, cooling, space, security, and often staff. Hosting cost/day = kWh/day × hosting rate. Self-hosting folds in energy, cooling overhead, fixed demand charges, labor, and the building itself: self-hosted all-in $/kWh = energy price × PUE + (fixed + O&M) × 12 ÷ (8760 × uptime) + (capex per kW ÷ life years) ÷ (8760 × uptime). The first term is grid energy scaled by PUE to capture cooling and power-delivery overhead; the second annualizes per-kW-month fixed and O&M charges across actual runtime hours; the third straight-line-amortizes infrastructure capex over its life per kWh of runtime. Self-hosting cost/day = kWh/day × self-hosted all-in rate. Net/day for each option = revenue/day (after pool fee) − cost/day, with monthly (×30.4) and annual (×365) projections. Annual cost per MW of miner load = 1000 kW × 8760 × uptime × $/kWh for each option — a site-level figure that strips out miner count so the two pricing models compare on equal footing regardless of fleet size. The breakeven self-hosting energy price solves for the energy price at which self-hosting all-in equals the hosting rate: breakeven = (hosting rate − fixed/O&M/capex components per kWh) ÷ PUE. Below that energy price, self-hosting beats hosting; above it, hosting wins. The side-by-side table highlights the option with the higher net/day, but the winner is entirely input-driven — which is why the self-hosting cost defaults are illustrative placeholders to be replaced with real quotes. Verification: Antminer S23 (318 TH/s, 3,498 W), qty 1, all defaults → revenue after pool fee = $12.03/day, kWh/day = 82.3, self-hosted all-in = $0.0885/kWh, hosting net = $5.45/day (~$1,989/yr), self-hosting net = $4.75/day (~$1,735/yr), annual cost/MW = $686,784 hosting vs $759,593 self-hosting, breakeven self-hosting energy ≈ $0.0423/kWh.

Open the calculator →

Halving impact

Blocks remaining = 1,050,000 − current height · Days to halving = blocks remaining ÷ 144 · Fees/block (absolute) = subsidy × fee% · Reward before = subsidy + fees · Reward after = subsidy ÷ 2 + fees · Hashprice ($/PH/s/day) = (1e15 ÷ (EH/s × 1e18)) × 144 × reward × BTC price · Breakeven $/kWh = (hashprice ÷ 1000) ÷ (J/TH × 0.024) · Revenue multiple = reward before ÷ reward after · BTC price to hold revenue = today's price × multiple · Net/day = share × 144 × reward × uptime × price × (1 − pool fee) − (W ÷ 1000) × 24 × uptime × $/kWh

The Bitcoin block subsidy halves every 210,000 blocks (~four years). The next halving lands at block 1,050,000, so blocks remaining = 1,050,000 − current height and days to halving = blocks remaining ÷ 144 (the ~144 blocks produced daily). The estimated date adds that many days to today; block times vary, so it is labeled an estimate. The revenue cut is not a clean 50% because transaction fees do not halve. Fees are paid per block in absolute BTC regardless of the subsidy, so this calculator converts the fee percentage into a fixed absolute amount first: fees per block = subsidy × fee%. Block reward before = subsidy + fees; after = subsidy ÷ 2 + fees. At the defaults (3.125 BTC, 3% fees) that is 3.21875 BTC before and 1.65625 BTC after — a 1.94× revenue multiple, not 2×. Hashprice ($/PH/s/day) = (1e15 ÷ (network EH/s × 1e18)) × 144 × block reward × BTC price, computed before and after. Holding hashrate and price flat, hashprice falls from about $39.40 to $20.27. Breakeven electricity ($/kWh) = (hashprice ÷ 1000) ÷ (J/TH × 0.024), where 0.024 kWh/TH/day = J/TH × 86,400 s ÷ 3,600,000. It drops from about $0.149/kWh to $0.077/kWh. The BTC price needed to hold revenue = today's price × (reward before ÷ reward after) — about $165,189 (1.94×), not a doubling. Miner net/day before and after uses the same share × 144 × reward × uptime × price × (1 − pool fee) − power cost formula as the ASIC Miner Profitability Calculator, applied to each reward and price in turn. Verification: defaults (height 971,398, 3.125 BTC, 3% fees, $85,000 price, 1,000 EH/s, 11 J/TH, $0.07/kWh, Antminer S23 318 TH/s 3,498 W, 2% pool fee, 98% uptime) → days to halving ≈ 546 (~April 2028), hashprice before ≈ $39.40 / after ≈ $20.27, breakeven before ≈ $0.149/kWh / after ≈ $0.077/kWh, BTC price to hold revenue ≈ $165,189 (1.94×), Antminer S23 net/day before ≈ $6.27 / after ≈ $0.43.

Open the calculator →

Hardware payback with difficulty growth

Network(m) = start EH/s × (1 + growth)^(m−1) · Reward(m) = subsidy(m) + fees/block · Revenue/day(m) = (TH/s × 1e12 ÷ (Network(m) × 1e18)) × 144 × reward(m) × uptime × BTC price · Net/day(m) = revenue × (1 − pool fee) − (W ÷ 1000) × 24 × uptime × $/kWh · Net(m) = net/day × 30.4 · Cumulative(m) = Σ net − hardware cost · Payback = first m with cumulative ≥ 0 · 36-mo ROI = cumulative(36) ÷ hardware cost

Static payback — hardware cost ÷ today's net/day — ignores the single biggest driver of mining returns: rising network difficulty. As more hashrate joins the Bitcoin network, a miner's share of the fixed daily block rewards shrinks, so the same machine earns less each month. This calculator models that decline month by month instead of assuming flat revenue. The model steps forward one month at a time. Network hashrate in month m = starting hashrate × (1 + monthly growth)^(m − 1), so a 1% monthly growth compounds the network to roughly 1.42× its starting level over 36 months. Revenue/day in month m = (miner hashrate in TH/s × 1e12 ÷ (network(m) in EH/s × 1e18)) × 144 × block reward(m) × uptime × BTC price, where block reward is the subsidy plus fees. If a halving is modeled, the subsidy halves from the chosen month onward while fees stay fixed in absolute BTC terms (they do not halve): fees per block = subsidy × fee%, a constant; reward(m) = subsidy(m) + fees per block. Net/day(m) = revenue/day × (1 − pool fee) − (W ÷ 1000) × 24 × uptime × $/kWh; the power cost is constant month to month, which is exactly why rising difficulty erodes net so quickly — revenue falls while power cost does not. Net(m) = net/day(m) × 30.4, and cumulative(m) = running sum of net(m) minus hardware cost (TH/s × $/TH). Payback month is the first month where cumulative turns positive; if it never does within the horizon, the calculator reports "not within horizon" rather than inventing a number. The 36-month ROI = cumulative(36) ÷ hardware cost, a single figure that folds in both the difficulty decline and the hardware outlay. The chart plots cumulative net against the hardware-cost line so the crossover is visible, and the table reports months 1, 12, 24, 36, 48, and 60. The sensitivity is the whole point: at the defaults an Antminer S23 pays back in month 36 with 1% monthly growth but in month 26 with 0% growth — a 10-month swing from a single percentage point of assumed growth. Verification: Antminer S23 (318 TH/s, 3,498 W), $15/TH hardware, $85,000 BTC, 1,000 EH/s start, 1% monthly growth, 3.125 BTC, 3% fees, 2% pool fee, $0.07/kWh, 98% uptime, 60-month horizon → hardware cost = $4,770, net/day month 1 ≈ $6.27, month 12 ≈ $5.03, month 24 ≈ $3.81, month 36 ≈ $2.73, payback month 36 (cumulative ≈ +$50); at 0% growth payback is month 26 and cumulative at month 36 ≈ +$2,095.

Open the calculator →

Curtailment & demand response revenue

Hashprice ($/PH/s/day) = (1e15 ÷ (network EH/s × 1e18)) × 144 × subsidy × (1 + fee%) × BTC price · Rev/miner kWh = (hashprice ÷ 1000) × (1 − pool fee) ÷ (J/TH × 0.024) · Rev/facility MWh = (rev/miner kWh × 1000) ÷ PUE · Curtailed MWh = facility MW × curtailed hours · Lost mining = curtailed MWh × rev/facility MWh · Power value = curtailed MWh × wholesale price · DR payments = facility MW × 1000 × $/kW-year × participation · Net = power value + DR − lost mining · Breakeven wholesale price = rev/facility MWh

Bitcoin mining is one of the most flexible large loads on the grid — a miner can ramp down in minutes — which makes curtailment (switching off) a revenue stream rather than just an operational nuisance. This calculator compares the mining revenue a facility gives up by curtailing against the value of the power it no longer consumes plus any demand-response payments, and finds the breakeven wholesale price above which curtailing beats mining. The revenue side is hashprice, the same figure the Hashprice & Breakeven Calculator derives. BTC per PH/s per day = (1e15 ÷ (network EH/s × 1e18)) × 144 × subsidy × (1 + fee%), and Hashprice ($/PH/s/day) = that × BTC price — about $39.40 at the defaults ($85,000 BTC, 1,000 EH/s, 3.125 BTC, 3% fees). To turn hashprice into a value per unit of facility energy, the calculator works down through miner efficiency and PUE. Mining revenue per miner kWh (after pool fee) = (hashprice ÷ 1000) × (1 − pool fee) ÷ (J/TH × 0.024), where J/TH × 0.024 is the kWh a terahash burns per day (J/TH × 86,400 s ÷ 3,600,000). Scaling that to the facility means dividing by PUE, because every miner kWh sits inside a larger facility draw that includes cooling and losses: Mining revenue per facility MWh = (revenue per miner kWh × 1000) ÷ PUE — about $127.17/MWh at the defaults (11 J/TH, 2% pool fee, 1.15 PUE). That figure is the breakeven wholesale price. Whenever the power a miner consumes is worth more than $127.17/MWh on the wholesale market, the facility earns more by switching off and selling (or not buying) that power than by mining. Curtailed energy (MWh) = facility MW × curtailed hours; lost mining revenue = curtailed MWh × revenue per facility MWh; value of power not consumed = curtailed MWh × wholesale price; and demand-response payments = facility kW × $/kW-year × participation %, for programs that pay standby capacity. Net curtailment benefit = power value + DR payments − lost mining revenue, also shown per curtailed MWh. The sensitivity table reports net benefit at wholesale prices of $75, $100, $150, $200, $300, and $500/MWh, holding lost mining revenue and DR payments fixed. Verification: 10 MW facility, 1.15 PUE, 11 J/TH, $85,000 BTC, 1,000 EH/s, 3.125 BTC, 3% fees, 2% pool fee, 200 curtailed hours, $200/MWh wholesale, $0/kW-year DR, 100% participation → hashprice ≈ $39.40/PH/s/day, mining revenue per facility MWh ≈ $127.17, curtailed energy = 2,000 MWh, lost mining revenue ≈ $254,345, value of power not consumed = $400,000, DR payments = $0, net benefit ≈ $145,655 ($72.83 per curtailed MWh), breakeven wholesale price ≈ $127.17/MWh.